In T-Mobile South v. City of Roswell the Supreme Court held 6-3 that the Telecommunications Act (TCA) requires local governments to provide reasons when denying an application to build a cell phone tower. The reasons do not have to be stated in the denial letter but must be articulated “with sufficient clarity in some other written record issued essentially contemporaneously with the denial,” which can include the council meeting minutes.
The Court agreed with the position in the State and Local Legal Center (SLLC)’s amicus brief that the reasons for a local government’s decision need not be in the same letter or document that denies the application and that council meeting minutes can be a sufficient source for the reasons for the denial. The Court disagreed, however, with the SLLC’s argument that the council minutes need not be issued contemporaneously with the document denying the wireless provider’s application.
T-Mobile applied to construct a 108-foot cell tower in a residential zoning area. Two days after a council hearing on the application, where city councilmembers voted to deny the application and stated various reasons for why they were going to vote against it, Roswell sent T-Mobile a brief letter stating that the application was denied and that T-Mobile could obtain hearing minutes from the city clerk. Twenty-six days later the minutes were approved and published.
The TCA requires that a state or local government's decision denying a cell tower construction permit be “in writing and supported by substantial evidence contained in a written record.”
The majority of the Court, in an opinion written by Justice Sotomayor, held that local governments have to provide reasons for why they are denying a cell tower application so that courts can determine whether the denial was supported by substantial evidence. The Court rejected, however, T-Mobile’s argument that the reasons must be set forth in a formal written decision denying the application instead of council meeting minutes because nothing in the TCA “imposes any requirement that the reasons be given in any particular form.” But the Court also held that, because wireless providers have only 30 days after an adverse decision to seek judicial review, the council meeting minutes setting forth the reasons have to be issued “essentially contemporaneous[ly]”with the denial.
The Court’s ruling that written minutes can meet the TCA’s “in writing” requirement is favorable to local governments, many of which routinely compile meeting minutes regardless of whether a cell tower application is being considered. But the Court’s requirement that a local government issue a denial letter and minutes at more or less the same time will be new to many local governments, and, as Chief Justice Roberts points out in his dissenting opinion, “could be a trap for the unwary hamlet or two.”
Following this decision, local governments should not issue any written denial of a wireless siting application until they (1) set forth the reasons for the denial in that written decision, or (2) make available to the wireless provider the final council meeting minutes or transcript of the meeting at which the action was taken.
Tim Lay, Jessica Bell, and Katharine Mapes of Spiegel & McDiarmid in Washington, D.C., wrote the SLLC’s brief which was joined by the National League of Cities, the United States Conference of Mayors, the National Association of Counties, the International City/County Management Association, and the International Municipal Lawyers Association.
New, Reduced Membership Dues
A new, reduced dues rate is available for CAOs/ACAOs, along with additional discounts for those in smaller communities, has been implemented. Learn more and be sure to join or renew today!